Renovation Update 01/11/2004
Click on any photo for a larger view
The
addition, bricked and ready for doors
and roof. The roof will hopefully go on yet
this winter if this nicer weather continues.
On
the left is the main side entrance door.
Center (below the light) will be the stage
work area entrance, and on the side is the
theater loading dock doors. The last two
obviously are note yet installed.
Another
view (front) of the new side addition
as Lee and Shane work to clean things up.
This
is difficult to see and understand, but it
will be a rolling plastic barrier that will wall
the "shop" area off them the rest of the
stage to protect from dust and such.
Here
Clark and Bryan finish up on the wall work
for the new costume area. The room above, the
"Shop" is similar in size and finish. Painting begins
tomorrow for both these rooms.